Biscuit Factory
Plots within the Biscuit Factory masterplan delivering social rent homes, on a tight, narrow site running alongside the railway.
- Homes
- 338
- Location
- Bermondsey
- Type
- Social rent homes
- Our role
- Programme, Project Execution Plan, Construction Management Plan and site logistics
What had to be planned
- Worked with the crane supplier to plan how each plot would be serviced
- Agreed hoarding, crane and hoist positions with the other plot developers and the master developer
- Agreed when and how the site could be serviced alongside neighbouring plots
- Prepared the full Project Execution Plan, CMP and programme

Planning documents on this scheme
Construction Programmes
Tender, contract and working programmes with a critical path you can defend.
View service PEPsProject Execution Plans
One document that sets out how the project will be delivered, by whom and when.
View service CMPs & CEMPsCMPs and CEMPs
Construction Management and Construction Environmental Management Plans that discharge planning conditions.
View service LogisticsSite Logistics Plans
Phased logistics drawings that show how the site works at every stage.
View serviceMore on construction planning in Central London and apartments and higher-risk buildings.

Bugsby's Way
Delivery strategy for a proposed multi-phase scheme built over the car park of a trading IKEA store, where parking had to stay live throughout.

Nine Elms Park
756 homes over a basement, with London Underground tunnels beneath, an old gas holder and a masterplan full of competing access rights.

St Michael's
Two towers of 23 and 20 storeys with a basement on a postage-stamp site between the bus station, the railway station and the tram line.