Bugsby's Way
Delivery strategy for a proposed multi-phase scheme built over the car park of a trading IKEA store, where parking had to stay live throughout.
- Homes
- 1,465
- Location
- Greenwich
- Type
- Apartments over a live car park
- Our role
- Programme, Project Execution Plan, Construction Management Plan and site logistics
What had to be planned
- Worked with IKEA on keeping the level of car parking its lease requires throughout construction
- Sequenced taking possession of the car park in three areas: build the podium, construct the buildings off it, then release the parking beneath
- Planned crane positions and logistics across a live retail operation
- Coordinated health and safety for tall buildings, multiple cranes and openings through slabs

Planning documents on this scheme
Construction Programmes
Tender, contract and working programmes with a critical path you can defend.
View service PEPsProject Execution Plans
One document that sets out how the project will be delivered, by whom and when.
View service CMPs & CEMPsCMPs and CEMPs
Construction Management and Construction Environmental Management Plans that discharge planning conditions.
View service LogisticsSite Logistics Plans
Phased logistics drawings that show how the site works at every stage.
View serviceMore on construction planning in South London and apartments and higher-risk buildings.

Nine Elms Park
756 homes over a basement, with London Underground tunnels beneath, an old gas holder and a masterplan full of competing access rights.

St Michael's
Two towers of 23 and 20 storeys with a basement on a postage-stamp site between the bus station, the railway station and the tram line.

Westminster Tower
Conversion of a riverside office tower by Lambeth Bridge, stripping and reinstating the façade and adding new floors on top.